Part 2 of 5 ยท See the summary of all five parts
Commitments tracker
Pandemic preparedness documents promise things by a date. We listed the dated commitments in each of the 26 jurisdictions' own strategy documents and checked whether each was delivered, as of 16 October 2026. Of the 170 commitments that had fallen due, 60 were delivered on time and 24 are overdue; 52 (31%) cannot be judged from public evidence. Another 125 itemised commitments are not yet due.
The pattern: one-off outputs such as new agencies, published plans and inquiry responses mostly arrive. Laws, operational capacity, evaluations and progress reports slip. This tracker measures whether governments kept their own promises. It does not measure how prepared a country is, and it does not change the benchmark scores.
How to read this
Something a government said it would do by a stated date, in its current strategy stack: the strategy itself, its responses to inquiries, and EU or WHO duties where these supply the only dates. Some rows bundle several commitments that share a date.
Each status was checked against official sources, legislation, audit reports and news on that date. A deadline given only as a year is read as 31 December of that year, and a fiscal year as its end date.
(on time + half of late and partial) รท items with a known status. Evidence coverage is the share of due items whose status could be established. Jurisdictions are ranked only with at least 3 known items.
Statuses
- On timeDelivered on or before the deadline. "Delivered" means published or established; it does not mean adequate.
- LateDelivered, but after the deadline.
- PartialPartly delivered, or delivered without the quantified level that was promised.
- OverdueDeadline passed and nothing delivered. Sometimes this rests on a search that found nothing; those items are flagged.
- Not yet dueThe deadline has not been reached.
- UnknownNo public evidence either way.
Caveats
- Coding uncertainty. The counts are one coding of the regional ledgers and should be read as plus or minus 2 per cell. Splitting matters: India's 20 advisory steps are counted one by one, while Singapore's White Paper yields only a handful of items.
- "Unknown" and absence of evidence. "Unknown" means no public evidence either way. Some "overdue" statuses rest on a search that found nothing; those rows are marked No publication found. Several official sites blocked access, so statuses that depend on them are reported, not verified.
- Selection effect. The ranking reflects how many, and what kind of, commitments each government chose to date. A government that dates only what it can already do scores well; one that dates hard laws and capacity can score badly; one that commits to nothing cannot fail. Read the index alongside evidence coverage and the number of dated items.
- "On time" is not "good enough". Delivered means published or established. Nobody assessed whether a guidance document or a bed agreement is adequate.
Totals across 26 jurisdictions
170 commitments had fallen due (or are standing). Delivery index 0.65; evidence coverage 69%. Counts are computed from the item list.
-
On time60
-
Late7
-
Partial27
-
Overdue24
-
Not yet due125
-
Unknown52
Ranking: delivery of self-set commitments
18 jurisdictions have at least 3 past-due items with a known status and are ranked; 8 have too few and are listed below them, with their index in brackets. Ties share a rank. "Not yet due" counts are lower bounds where actions were not itemised.
| Rank | Jurisdiction | On time | Late | Partial | Overdue | Unknown | Not yet due | Delivery index | Evidence coverage | Main caveat |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | ๐น๐ผ Taiwan | 8 | 0 | 0 | 0 | 4 | 2 | 1.00 | 67% | All delivered items are 2024 KPIs or agency-controlled outputs; 2025 results not public |
| 2 | ๐ฏ๐ต Japan | 7 | 0 | 1 | 0 | 0 | 3 | 0.94 | 100% | Targets benchmarked on COVID capacity; 4 further items delivered only by claim |
| 3 | ๐ธ๐ฌ Singapore | 4 | 0 | 1 | 0 | 3 | 0 | 0.90 | 63% | Only the CDA date was a true deadline; capacity items undated by design |
| 4 | ๐ฐ๐ท South Korea | 3 | 0 | 1 | 0 | 3 | 9 | 0.88 | 57% | 2023/2024 quantified targets not reported against |
| 5 | ๐จ๐ญ Switzerland | 2 | 0 | 1 | 0 | 1 | 4 | 0.83 | 75% | Capacity commitments deferred to 2027+ |
| 6 | ๐ฉ๐ฐ Denmark | 3 | 0 | 2 | 0 | 0 | 3 | 0.80 | 100% | Strategy itself has no dated commitments; items come from audit follow-up |
| 7 | ๐ฌ๐ง United Kingdom | 5 | 0 | 1 | 1 | 1 | 24 | 0.79 | 88% | Real test is March 2027 (16 short-term actions) |
| 8 | ๐ฉ๐ช Germany | 2 | 1 | 1 | 0 | 1 | 3 | 0.75 | 80% | NPP revision undated, so it cannot count as overdue |
| 9 | ๐ณ๐ฌ Nigeria | 3 | 1 | 4 | 0 | 2 | 0 | 0.69 | 80% | Score lifted by recurring WHO reporting |
| 10 | ๐ช๐บ European Union | 6 | 1 | 2 | 3 | 2 | 15 | 0.63 | 86% | Many 2026 items "not due" but shown as in progress by HERA |
| 11 | ๐ง๐ท Brazil | 2 | 0 | 2 | 1 | 1 | 2 | 0.60 | 83% | Central deliverable (pandemic plan) is the overdue item |
| 12= | ๐ฎ๐ฑ Israel | 2 | 0 | 1 | 2 | 2 | 0 | 0.50 | 71% | Operational layer delivered, strategic layer not |
| 12= | ๐ณ๐ฟ New Zealand | 1 | 1 | 0 | 1 | 1 | 31 | 0.50 | 75% | Only 1 of 32 response actions due yet |
| 12= | ๐ณ๐ด Norway | 1 | 0 | 3 | 1 | 0 | 1 | 0.50 | 100% | Pandemiplanen undated, in drafting since 2024 |
| 15 | ๐ฎ๐น Italy | 0 | 1 | 1 | 1 | 1 | 8 | 0.33 | 75% | Overdue item is a legacy commitment (DL 34/2020 ICU beds) |
| 16= | ๐ฆ๐น Austria | 0 | 0 | 3 | 2 | 1 | 1 | 0.30 | 83% | Audit office counts "promised" as implemented |
| 16= | ๐ช๐ธ Spain | 1 | 1 | 0 | 3 | 0 | 2 | 0.30 | 100% | Two overdue items re-promised for end-2026 |
| 18 | ๐ฎ๐ณ India | 1 | 0 | 2 | 6 | 12 | 0 | 0.22 | 43% | NITI roadmap is advisory; 6 "overdue" rest mostly on absence of evidence |
| Too few checkable items to rank (fewer than 3 with a known status) | ||||||||||
| โ | ๐ซ๐ฎ Finland | 2 | 0 | 0 | 0 | 4 | 0 | (1.00) | 33% | Plan sets no dates; one item is an EU Art. 8(3) duty |
| โ | ๐ธ๐ช Sweden | 2 | 0 | 0 | 0 | 0 | 2 | (1.00) | 100% | Delivered items are inquiry reports; no strategy adopted |
| โ | ๐น๐ญ Thailand | 2 | 0 | 0 | 0 | 4 | 3 | (1.00) | 33% | Both items self-reported (SPAR, EMT claim) |
| โ | ๐จ๐ฆ Canada | 1 | 0 | 1 | 0 | 0 | 4 | (0.75) | 100% | Core content published only as an e-learning module |
| โ | ๐ฎ๐ฉ Indonesia | 1 | 1 | 0 | 0 | 2 | 5 | (0.75) | 50% | Plan only about 10 months old |
| โ | ๐ฆ๐บ Australia | 1 | 0 | 0 | 1 | 3 | 1 | (0.50) | 40% | Only the CDC was hard-dated |
| โ | ๐บ๐ธ United States | 0 | 0 | 0 | 2 | 2 | 2 | (0.00) | 50% | Incident-relative targets; tracking internal; unauditable |
| โ | ๐ซ๐ท France | 0 | 0 | 0 | 0 | 2 | 0 | n/a | 0% | No public, dated plan commitments |
| Total (26) | 60 | 7 | 27 | 24 | 52 | 125 | 0.65 | 69% | ||
Computed from the item list
Every count, index and rank on this page is calculated from the ledgers below, so they change when a status is updated. They match the full report's table.
Ledgers: what each government promised and what arrived
Open a jurisdiction to see each commitment, its deadline, where it was made and the evidence for its status.
Anglosphere
๐ฌ๐ง United Kingdom Index 0.79 ยท coverage 88% 5 on time1 partial1 overdue24 not yet due1 unknown
The March 2026 strategy sets an "indicative" timeline: 16 short-term actions by March 2027, about 40 for 2027โ28, more for 2028โ30, and a review in 2028. Dated outputs so far arrived on time; the six-monthly Inquiry updates did not.
-
On time
Publish new guidance on spending controls in a crisis
- Due
- In 2026
- Committed in
- Pandemic Preparedness Strategy (Mar 2026)
- Evidence
- HM Treasury published Spending in a Crisis on 20 May 2026. Source, 20 May 2026 (opens in a new tab)
-
On time
Respond to the COVID-19 Inquiry Module 1 report within six months
- Due
- 18 Jan 2025
- Committed in
- UK COVID-19 Inquiry, Module 1
- Evidence
- UK Government response published 16 Jan 2025. Source, 16 Jan 2025 (opens in a new tab)
-
On time
Respond to the COVID-19 Inquiry Module 2 report
- Due
- 20 May 2026
- Committed in
- UK COVID-19 Inquiry, Module 2
- Evidence
- Response (CP 1534) published 25 Mar 2026, the same day as the strategy. Source, 25 Mar 2026 (opens in a new tab)
-
On time
Hold a national pandemic exercise (Exercise Pegasus) in autumn 2025
- Due
- Autumn 2025
- Committed in
- Module 1 response (Jan 2025)
- Evidence
- Exercise phases ran from September 2025, with further phases on 9 and 30 October. Source, 30 Sep 2025 (opens in a new tab)
-
On time
Publish annual Biological Security Strategy implementation reports
- Due
- Annual
- Committed in
- UK Biological Security Strategy (2023)
- Evidence
- Reports published 8 Jul 2025 and 14 Jul 2026 (self-assessed, no ratings). Source, 14 Jul 2026 (opens in a new tab)
-
Partial
Expand metagenomic surveillance to 30 NHS sites
- Due
- Standing (no date for the 30-site target)
- Committed in
- Pandemic Preparedness Strategy (Mar 2026), pp.47โ48
- Evidence
- The BSS 2026 report counts 18 active NHS sites against the 30-site target. Source, 14 Jul 2026 (opens in a new tab)
-
Overdue
Publish six-monthly Module 1 implementation updates, as the Inquiry Chair requested
- Due
- Jan 2026 and Jul 2026
- Committed in
- UK COVID-19 Inquiry, Module 1; Cabinet Office written answer (Sep 2025)
- Evidence
- No publication foundLast UK Government update found is dated 8 Jul 2025. No publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Fund new platform trials in spring 2026
- Due
- Spring 2026
- Committed in
- Pandemic Preparedness Strategy (Mar 2026)
- Evidence
- An NIHR call closed in Sep 2025; no 2026 award announcement found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Prepare a draft All Pandemic Hazards Bill
- Due
- 31 Mar 2027
- Committed in
- Pandemic Preparedness Strategy (Mar 2026)
- Evidence
- No draft clauses or parliamentary record found yet. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Adapt the respiratory pandemic plan for the other four routes of transmission
- Due
- In 2026
- Committed in
- Pandemic Preparedness Strategy (Mar 2026)
- Evidence
- No publication yet; the year ends 31 Dec 2026. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
The other 12 short-term actions (for example lead-department expectations, crisis communications plan, PPE replenishment, data and modelling review, hospital discharge plan) (12 commitments)
- Due
- 31 Mar 2027
- Committed in
- Pandemic Preparedness Strategy (Mar 2026), pp.62โ67
- Evidence
- No progress report on the strategy itself; no evidence of completion found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Publish the full Exercise Pegasus report
- Due
- Winter 2026
- Committed in
- Pandemic Preparedness Strategy; Module 2 response, Rec 14
- Evidence
- Recommitted in the BSS report of 14 Jul 2026. Source, 14 Jul 2026 (opens in a new tab)
-
Not yet due
Refresh expert selection processes (Rec 3) and update guidance on publishing technical advice (Rec 4) (2 commitments)
- Due
- In 2026
- Committed in
- Module 2 response (Mar 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Agree four-nation crisis-communication principles (Rec 17)
- Due
- In 2026
- Committed in
- Module 2 response (Mar 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Review advisory-group terms of reference (Rec 5)
- Due
- By 2027
- Committed in
- Module 2 response (Mar 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Lay the Civil Contingencies Act post-implementation review (Rec 16)
- Due
- 31 Mar 2027
- Committed in
- Module 2 response (Mar 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Understand supply-chain risks for testing (UKHSA); operational action plan for adult social care (DHSC) (2 commitments)
- Due
- By 2027
- Committed in
- Pandemic Preparedness Strategy (Mar 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Start infection prevention and control training
- Due
- 2026โ27
- Committed in
- Pandemic Preparedness Strategy (Mar 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Review the strategy
- Due
- In 2028
- Committed in
- Pandemic Preparedness Strategy (Mar 2026), p.67
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- About 40 medium-term (2027โ28) and about 25 long-term (2028โ30) strategy actions: not itemised.
๐บ๐ธ United States Index 0.00 (too few items to rank) ยท coverage 50% 2 overdue2 not yet due2 unknown
Most of the National Biodefense Strategy's 32 targets run from the declaration of an incident, so they cannot be "delivered" until an event tests them. The strategy is formally in force but effectively unimplemented as a plan.
-
Overdue
Help 50 countries directly, and 50 more catalytically, reach "demonstrated capacity"
- Due
- By 2025
- Committed in
- National Biodefense Strategy and Implementation Plan (Oct 2022), target 2.1.1
- Evidence
- No publication foundLast public figure: seven partner countries in FY2022; the WHO exit completed 22 Jan 2026. No publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 30 Dec 2023 (opens in a new tab)
-
Overdue
Keep the statutory basis in place (PAHPA reauthorisation)
- Due
- 30 Sep 2023
- Committed in
- National Biodefense Strategy stack
- Evidence
- Authorisation lapsed 30 Sep 2023; some provisions extended only to 31 Dec 2026; no reauthorisation bill. Source, 16 Feb 2026 (opens in a new tab)
-
Unknown
Publish seven joint capabilities plans (early warning, biosafety, diagnostics, PPE, vaccines, therapeutics, clinical trials)
- Due
- Undated (expected during implementation)
- Committed in
- National Biodefense Strategy and Implementation Plan (Oct 2022)
- Evidence
- None published; whether any were drafted internally is unknown. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Be able to make vaccines within 100 days, and enough for the US population within 130 days
- Due
- Standing capability
- Committed in
- National Biodefense Strategy and Implementation Plan (Oct 2022)
- Evidence
- No assessment found; HHS wound down BARDA mRNA work in Aug 2025. Source, 5 Aug 2025 (opens in a new tab)
-
Not yet due
FDA approval of at least two novel antivirals ready for stockpiling
- Due
- About Oct 2027
- Committed in
- National Biodefense Strategy and Implementation Plan, target 3.5.2
- Evidence
- No tracking source found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
HHS Pandemic Influenza Plan horizon (2017โ2027)
- Due
- In 2027
- Committed in
- HHS Pandemic Influenza Plan (2017)
- Evidence
- Still the latest plan; no replacement found. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- About 66 NBS-IP actions: not itemised.
- Incident-relative capability targets (12-hour diagnostics, 90-day PPE surge, therapeutics in 90 days or six months): no calendar date.
๐จ๐ฆ Canada Index 0.75 (too few items to rank) ยท coverage 100% 1 on time1 partial4 not yet due
The core content of the new plan appeared by the end of June 2026 as promised, but only as an e-learning module (down on 13 Oct, readable again on 18 Oct 2026). Most commitments are framed in fiscal years and fall due in 2026โ27 or later.
-
On time
Release the core content of the new pandemic plan
- Due
- 30 Jun 2026
- Committed in
- PHAC, Canada's Pandemic Preparedness Plan
- Evidence
- Released about 29 Jun 2026, only as an e-learning module (offline 13 Oct, readable 18 Oct 2026; no PDF). Source, 29 Jun 2026 (opens in a new tab)
-
Partial
Fix the national stockpile weaknesses found by the Auditor General in 2021
- Due
- 31 Mar 2025
- Committed in
- OAG Reports 8 and 10 (2021), PHAC action plan
- Evidence
- Only partly resolved; about $20m of medication was lost in Dec 2024. Source, 1 Feb 2026 (opens in a new tab)
-
Not yet due
Finalise and publish the pandemic plan
- Due
- 2026โ27 (by 31 Mar 2027)
- Committed in
- PHAC Departmental Plan 2026โ27
- Evidence
- Core content released; technical components pending. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Update antiviral and National Emergency Strategic Stockpile recommendations
- Due
- 2026โ27 (by 31 Mar 2027)
- Committed in
- PHAC Departmental Plan 2026โ27
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Publish the five technical components
- Due
- Throughout 2027
- Committed in
- PHAC, About the new pandemic plan
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Secure pandemic vaccine readiness agreements for 2028 onward
- Due
- 2028 onward
- Committed in
- PHAC Departmental Plan 2026โ27
- Evidence
- A request for information ran 22 Jun โ 7 Aug 2026. Source, 7 Aug 2026 (opens in a new tab)
๐ฆ๐บ Australia Index 0.50 (too few items to rank) ยท coverage 40% 1 on time1 overdue1 not yet due3 unknown
The statutory Australian CDC started on 1 January 2026 as promised. The formal response to the COVID-19 Response Inquiry has not been found, and the rest of the Inquiry agenda has no public tracker.
-
On time
Start the statutory Australian Centre for Disease Control
- Due
- 1 Jan 2026
- Committed in
- Government commitment (Oct 2024); Australian CDC Act 2025
- Evidence
- The agency started on 1 Jan 2026; its Director-General started on 1 Mar 2026. Source, 1 Jan 2026 (opens in a new tab)
-
Overdue
Release a formal response to the COVID-19 Response Inquiry
- Due
- After the Oct 2024 report (no date)
- Committed in
- Prime Minister's media release (29 Oct 2024)
- Evidence
- No publication foundNo publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Carry out the Inquiry's 19 "immediate actions"
- Due
- Within 12โ18 months (about Apr 2026)
- Committed in
- COVID-19 Response Inquiry Report (Oct 2024)
- Evidence
- No public implementation tracker found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Hold biennial preparedness reviews (CDC with NEMA)
- Due
- Every two years
- Committed in
- COVID-19 Response Inquiry Report, Action 7
- Evidence
- No first review found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Table the CDC's first annual report to Parliament (2025โ26)
- Due
- About Oct 2026
- Committed in
- Australian CDC Act 2025
- Evidence
- Not found yet. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Review the CDC's remit, including chronic disease
- Due
- In 2028
- Committed in
- Australian CDC legislation and funding
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Review of the 2019 pandemic influenza plan (AHMPPI): "currently under review" since August 2026, with no completion date.
๐ณ๐ฟ New Zealand Index 0.50 ยท coverage 75% 1 on time1 late1 overdue31 not yet due1 unknown
New Zealand has the most precisely dated ledger: 32 actions, each with a lead agency, a status and a deadline. Twenty of them fall due on 30 June 2027, and ten had not started at publication.
-
On time
Issue a Cabinet Office circular on releasing key pandemic advice within five working days (Action 2.1)
- Due
- 30 Sep 2026
- Committed in
- Government Response to the Royal Commission (Jul 2026), Annex 2
- Evidence
- Reportedly issued 28 Sep 2026 as CO (26) 6; the DPMC page could not be opened to confirm. Source, 28 Sep 2026 (opens in a new tab)
-
Late
Independent review of the Reserve Bank's COVID monetary policy
- Due
- Aug 2026
- Committed in
- Government Response to the Royal Commission (Jul 2026)
- Evidence
- Released about 22 Sep 2026, roughly a month late. Source, 22 Sep 2026 (opens in a new tab)
-
Overdue
Carry out a "more substantive review" of the interim pandemic plan
- Due
- 2024/25 (by 30 Jun 2025)
- Committed in
- Interim NZ Pandemic Plan (Jul 2024), p.4
- Evidence
- Not delivered; folded into Action 4.1, now due 30 Jun 2027. Source, 29 Jul 2026 (opens in a new tab)
-
Unknown
Publish periodic progress updates on the response
- Due
- Periodic (no date)
- Committed in
- Government Response to the Royal Commission, s1.4
- Evidence
- None found under three months after publication; the Ministry site blocked access. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Actions 2.5, 3.2, 5.3 and 5.4 (4 commitments)
- Due
- 31 Dec 2026
- Committed in
- Government Response, Annex 2
- Evidence
- Two of the four (5.3, 5.4) were "not yet started" at publication. Source, 29 Jul 2026 (opens in a new tab)
-
Not yet due
Actions 4.4 and 7.4 (2 commitments)
- Due
- 31 Mar 2027
- Committed in
- Government Response, Annex 2
- Evidence
- Not yet due. Source, 29 Jul 2026 (opens in a new tab)
-
Not yet due
20 actions, including the strategic framework and all-of-government plan (4.1), the exercise programme (4.3) and modelling (3.1) (20 commitments)
- Due
- 30 Jun 2027
- Committed in
- Government Response, Annex 2
- Evidence
- Several, including 4.3, 6.1 and 7.1, were "not yet started" at publication. Source, 29 Jul 2026 (opens in a new tab)
-
Not yet due
Actions 1.1, 1.2 and 7.2 (3 commitments)
- Due
- OctโDec 2029
- Committed in
- Government Response, Annex 2
- Evidence
- Not yet due. Source, 29 Jul 2026 (opens in a new tab)
-
Not yet due
Health Act review (5.1) and Action 6.4 (2 commitments)
- Due
- FY2028 onward
- Committed in
- Government Response, Annex 2
- Evidence
- Action 5.1 was "not yet started" at publication. Source, 29 Jul 2026 (opens in a new tab)
East Asia and Singapore
๐ฏ๐ต Japan Index 0.94 ยท coverage 100% 7 on time1 partial3 not yet due
Every dated item that has fallen due was delivered. The capacity targets were set against COVID-era peaks and met through signed agreements, which is paper capacity.
-
On time
Launch the Japan Institute for Health Security (JIHS)
- Due
- 1 Apr 2025
- Committed in
- JIHS Act
- Evidence
- Launched on the statutory date, 1 Apr 2025. Source, 11 Apr 2025 (opens in a new tab)
-
On time
Start acute respiratory infection (ARI) surveillance
- Due
- Apr 2025
- Committed in
- Government Action Plan (Jul 2024)
- Evidence
- Started April 2025. Source, 16 Jul 2026 (opens in a new tab)
-
On time
Turn the 2021 vaccine strategy into a medical countermeasures strategy
- Due
- FY2025
- Committed in
- FY2025 follow-up
- Evidence
- Cabinet decision of 24 Mar 2026. Source, 24 Mar 2026 (opens in a new tab)
-
On time
Publish an annual follow-up of the Action Plan
- Due
- Every fiscal year
- Committed in
- Government Action Plan (Jul 2024), p.55
- Evidence
- Published June 2025 and 16 Jul 2026 (no delivered/not-delivered judgments). Source, 16 Jul 2026 (opens in a new tab)
-
On time
Secure 45,681 beds through prefectural agreements
- Due
- From Apr 2024
- Committed in
- Prefectural plans under the Action Plan
- Evidence
- 49,179 beds as of 1 Oct 2025 (signed agreements, not drill-tested). Source, 1 Oct 2025 (opens in a new tab)
-
On time
Secure 41,643 fever clinics
- Due
- From Apr 2024
- Committed in
- Prefectural plans under the Action Plan
- Evidence
- 41,917 as of 1 Oct 2025. Source, 1 Oct 2025 (opens in a new tab)
-
On time
Testing capacity of about 100,000 a day early and 440,000 a day later
- Due
- From Apr 2024
- Committed in
- Prefectural plans under the Action Plan
- Evidence
- About 260,000 and 500,000 a day as of 1 Oct 2025. Source, 1 Oct 2025 (opens in a new tab)
-
Partial
Run the SCARDA vaccine research programme
- Due
- Ongoing
- Committed in
- Vaccine strategy (2021)
- Evidence
- 36 projects adopted; no milestone to judge against. Source, 16 Jul 2026 (opens in a new tab)
-
Not yet due
First annual follow-up of the countermeasures strategy
- Due
- About FY2026
- Committed in
- MCM strategy (Mar 2026), p.20
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Dual-use vaccine manufacturing: 8 manufacturing, 4 fill-finish and 4 clinical-batch sites
- Due
- FY2028 (to Mar 2029)
- Committed in
- Vaccine manufacturing subsidy programme
- Evidence
- Construction "starting in sequence"; METI flagged weak outcome indicators. Source, 16 Jul 2026 (opens in a new tab)
-
Not yet due
Revise the Action Plan
- Due
- Roughly every six years (about 2030)
- Committed in
- Government Action Plan (Jul 2024)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Four further items delivered by government claim only (border agreements, public health centre plans, clinical research network, exercises): not counted.
๐ฐ๐ท South Korea Index 0.88 ยท coverage 57% 3 on time1 partial9 not yet due3 unknown
Both interim deliverables of the June 2026 plan arrived on time, and both were follow-ups to a February 2026 audit. Quantified targets from the 2023 and 2024 plans are not reported against.
-
On time
Enact an infectious-disease crisis social-response manual
- Due
- Aug 2026
- Committed in
- 2026 crisis-management plan (Jun 2026)
- Evidence
- Enacted 18 Aug 2026, as a follow-up to the February audit. Source, 18 Aug 2026 (opens in a new tab)
-
On time
Plan to improve vaccine quality control and safe vaccination
- Due
- Sep 2026
- Committed in
- 2026 crisis-management plan; work report (Jul 2026)
- Evidence
- Announced by KDCA and MFDS on 30 Sep 2026. Source, 30 Sep 2026 (opens in a new tab)
-
On time
Check delivery of the 2023 plan quarterly, then half-yearly
- Due
- 2024โ25
- Committed in
- 2023 mid- to long-term plan
- Evidence
- Six checks held, but their results were never published. Source, 10 Jun 2026 (opens in a new tab)
-
Partial
Start Phase 2 trials of a domestic COVID mRNA vaccine
- Due
- Aug 2026
- Committed in
- 2026 work report
- Evidence
- Funding started and the trial was approved on 11 Sep 2026; no participant dosed yet. Source, 11 Sep 2026 (opens in a new tab)
-
Unknown
Build 1,700 emergency beds (about 3,500 beds overall)
- Due
- 2023 onward
- Committed in
- 2023 mid- to long-term plan
- Evidence
- The 2026 plan cites 938 emergency beds; not reported against the target. Source, 10 Jun 2026 (opens in a new tab)
-
Unknown
Antivirals for 25% of the population; nine PPE items; six months' supplies
- Due
- By 2027
- Committed in
- 2024 pandemic influenza plan
- Evidence
- No stock report found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Vaccinate the whole population within 30 days (2.2 million a day)
- Due
- Standing capability
- Committed in
- 2023 mid- to long-term plan
- Evidence
- Untested; the 2026 plan re-commits to the booking capacity. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Publish the 4th national infectious-disease R&D strategy (2027โ31)
- Due
- Nov 2026
- Committed in
- KDCA work report (Jul 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Unify bed management under KDCA and re-designate institutions
- Due
- Dec 2026
- Committed in
- KDCA work report (Jul 2026)
- Evidence
- Official bed figures conflict (597 vs 270). Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Five-syndrome multiplex assay and a nationwide testing network within 30 days
- Due
- Dec 2026
- Committed in
- KDCA work report (Jul 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
KoreaโChinaโJapan infectious-disease forum
- Due
- Dec 2026
- Committed in
- KDCA work report (Jul 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Set up a separate crisis-funding mechanism
- Due
- About 2026
- Committed in
- 2026 crisis-management plan, p.19
- Evidence
- No legislation or budget line found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Expand influenza sentinel sites to 1,000
- Due
- By 2027
- Committed in
- 2024 pandemic influenza plan
- Evidence
- On track: 800 sites in the first half of 2026. Source, 15 Jul 2026 (opens in a new tab)
-
Not yet due
AI prediction engine and a clinical research centre
- Due
- 2027 and 2030
- Committed in
- KDCA work report (Jul 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Specialised infectious-disease hospitals
- Due
- 2027โ33
- Committed in
- KDCA (Jul 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
License a domestic COVID mRNA vaccine
- Due
- In 2028
- Committed in
- mRNA programme (โฉ505.2bn, 2025โ28)
- Evidence
- At risk: only one developer remains in the programme. Source, 16 Oct 2026 (opens in a new tab)
๐น๐ผ Taiwan Index 1.00 ยท coverage 67% 8 on time2 not yet due4 unknown
Taiwan CDC's 2024 results annex shows every checked KPI met. The 2025 results and the new medical-network KPIs are not public.
-
On time
Keep antiviral stocks for at least 10% of the population
- Due
- 2024 (annual)
- Committed in
- 2022โ2027 preparedness plan (Jun 2024 revision), KPI
- Evidence
- 12.7% of the population in the 2024 results annex. Source, 29 Aug 2025 (opens in a new tab)
-
On time
Keep central PPE safety stock at 100%
- Due
- 2024 (annual)
- Committed in
- 2022โ2027 preparedness plan, KPI
- Evidence
- 100% in the 2024 results annex. Source, 29 Aug 2025 (opens in a new tab)
-
On time
Add one new emerging-disease test method a year
- Due
- 2024 (annual)
- Committed in
- 2022โ2027 preparedness plan, KPI
- Evidence
- One method added in 2024. Source, 29 Aug 2025 (opens in a new tab)
-
On time
Training and exercises
- Due
- 2024 (annual)
- Committed in
- 2022โ2027 preparedness plan, KPI
- Evidence
- 497 sessions, 43,474 attendances in 2024. Source, 29 Aug 2025 (opens in a new tab)
-
On time
Inspect and correct all select-agent laboratories
- Due
- 2024
- Committed in
- 2022โ2027 preparedness plan, KPI
- Evidence
- 12 inspections reported. Source, 29 Aug 2025 (opens in a new tab)
-
On time
IHR port self-assessment and external evaluation
- Due
- 2024 (annual)
- Committed in
- 2022โ2027 preparedness plan, KPI
- Evidence
- External evaluation at four designated ports in 2024. Source, 29 Aug 2025 (opens in a new tab)
-
On time
Two special-pathogen care centres
- Due
- In 2025
- Committed in
- 2022โ2027 preparedness plan (Jun 2024 revision)
- Evidence
- Three centres operating by August 2025. Source, 7 Aug 2025 (opens in a new tab)
-
On time
Execute the plan budget
- Due
- Annual
- Committed in
- 2022โ2027 preparedness plan
- Evidence
- 100% execution in 2022โ23 (ministry claim). Source, 1 Jan 2024 (opens in a new tab)
-
Unknown
Publish 2025 KPI results
- Due
- About Aug 2026
- Committed in
- 2022โ2027 preparedness plan
- Evidence
- The 2025 results annex was not found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Six regional coordination offices
- Due
- In 2025
- Committed in
- 2022โ2027 preparedness plan (Jun 2024 revision)
- Evidence
- No public evidence found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Hospital zoning and tiered-response KPIs (zoned triage 30%; about 30 response hospitals)
- Due
- In 2025
- Committed in
- 2022โ2027 preparedness plan (Jun 2024 revision)
- Evidence
- No 2025 results found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Act on the White Paper's 56 recommendations
- Due
- Not dated
- Committed in
- Post-COVID White Paper (2024)
- Evidence
- No tracking report found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Six regional drills
- Due
- In 2026
- Committed in
- 2022โ2027 preparedness plan
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
2027 targets: five new test methods, negative-pressure pass rate 100%, cross-region drills
- Due
- In 2027
- Committed in
- 2022โ2027 preparedness plan
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Post-COVID overhaul of the Communicable Disease Control Act: never dated; not passed.
๐ธ๐ฌ Singapore Index 0.90 ยท coverage 63% 4 on time1 partial3 unknown
The institutional and legal commitments are delivered. The capacity commitments are undated and have no public evidence.
-
On time
Amend the Infectious Diseases Act to add graduated public-health postures
- Due
- After the White Paper
- Committed in
- White Paper on COVID-19 (Mar 2023)
- Evidence
- In force 9 Apr 2024 (Act 13 of 2024). Source, 9 Apr 2024 (opens in a new tab)
-
On time
Set up the Communicable Diseases Agency
- Due
- Apr 2025
- Committed in
- Government announcement
- Evidence
- Operational April 2025; launched 12 Nov 2025. Source, 12 Nov 2025 (opens in a new tab)
-
On time
Run the PREPARE research programme
- Due
- Five-year programme
- Committed in
- White Paper on COVID-19 (Mar 2023)
- Evidence
- Running under the agency, with 2026 grant rounds. Source, 16 Oct 2026 (opens in a new tab)
-
On time
Keep supporting CEPI
- Due
- Ongoing
- Committed in
- White Paper on COVID-19 (Mar 2023)
- Evidence
- USD 12m over four years pledged in May 2026. Source, 1 May 2026 (opens in a new tab)
-
Partial
Review stockpiling and build local production in selected areas
- Due
- Not dated
- Committed in
- White Paper on COVID-19 (Mar 2023)
- Evidence
- Biofoundries set up (claim); no stockpile review published. Source, 25 Sep 2026 (opens in a new tab)
-
Unknown
Hold regular exercises and simulations
- Due
- Regular (no date)
- Committed in
- Pandemic Preparedness and Response Framework (2025)
- Evidence
- No national pandemic exercise found in 2025โ26. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Be able to vaccinate more than half the population in 3โ4 weeks
- Due
- Standing
- Committed in
- White Paper on COVID-19 (Mar 2023)
- Evidence
- No public test or report. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Expand the National Centre for Infectious Diseases
- Due
- Not dated
- Committed in
- White Paper on COVID-19 (Mar 2023)
- Evidence
- No expansion project found; the centre's role was narrowed. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- "Refresh national pandemic plans": delivered by claim; the 2025 framework is published.
European Union and its big four
๐ช๐บ European Union Index 0.63 ยท coverage 86% 6 on time1 late2 partial3 overdue15 not yet due2 unknown
Flagship documents arrived on schedule. Implementation items and evaluations slipped, and HERA's 2026 work plan quietly re-dates several of them.
-
On time
Adopt a Medical Countermeasures (MCM) Strategy
- Due
- In 2025
- Committed in
- Preparedness Union Strategy action plan (Mar 2025)
- Evidence
- Adopted 9 Jul 2025 as COM(2025) 529. Source, 9 Jul 2025 (opens in a new tab)
-
On time
Publish the Union prevention, preparedness and response plan
- Due
- In 2025
- Committed in
- Preparedness Union Strategy; Reg. 2022/2371 Art. 5
- Evidence
- COM(2025) 745 and SWD(2025) 393, 28 Nov 2025. Source, 28 Nov 2025 (opens in a new tab)
-
On time
First round of Member State preparedness reports (Art. 7)
- Due
- 27 Dec 2023
- Committed in
- Regulation (EU) 2022/2371
- Evidence
- All 30 EU/EEA countries reported in 2023. Source, 27 Dec 2023 (opens in a new tab)
-
On time
First Commission report to Parliament and Council (Art. 9)
- Due
- 27 Dec 2023
- Committed in
- Regulation (EU) 2022/2371
- Evidence
- COM(2023) 792; exact adoption date not verified. Source, 1 Dec 2023 (opens in a new tab)
-
On time
Launch the MCM Accelerator
- Due
- In 2025
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- First actions launched; a contract signed at the end of 2025. Source, 31 Dec 2025 (opens in a new tab)
-
On time
Publish crisis procurement guidelines
- Due
- In 2026
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- Handbook for EU crisis procurement of MCMs published 9 Sep 2026. Source, 9 Sep 2026 (opens in a new tab)
-
Late
Publish the 2025 health threat prioritisation assessment
- Due
- Late 2025
- Committed in
- MCM Strategy, Annex 1
- Evidence
- SWD(2026) 1 dated 8 Jan 2026, about a week late. Source, 8 Jan 2026 (opens in a new tab)
-
Partial
Launch Medifence, a civilโmilitary MCM initiative
- Due
- In 2025
- Committed in
- MCM Strategy (box says 2025; text says 2026)
- Evidence
- No formal launch found; related expert-group and defence calls exist. Source, 16 Oct 2026 (opens in a new tab)
-
Partial
Hold global pooled-procurement workshops with partners
- Due
- In 2025
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- First workshop slipped to mid-January 2026. Source, 15 Jan 2026 (opens in a new tab)
-
Overdue
Publish a compendium of MCMs suitable for EU stockpiling
- Due
- Q3 2025
- Committed in
- MCM Strategy, Annex 2
- Evidence
- No publication foundHERA's 2026 work plan still lists it as future work. No publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Overdue
Evaluate Regulation (EU) 2022/2371
- Due
- Q1 2026
- Committed in
- Union PPR plan, COM(2025) 745
- Evidence
- No publication foundNo publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Overdue
Evaluate ECDC
- Due
- Q2 2026
- Committed in
- Union PPR plan, COM(2025) 745
- Evidence
- No publication foundNo publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Classified draft quantification of stockpile needs
- Due
- Q1 2026
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- Classified by design, so it cannot be checked publicly. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Full roll-out of the shelf-life extension programme
- Due
- Q3 2026
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- HERA "will continue piloting"; no roll-out evidence found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Publish the first EU List of MCMs for Priority Threats
- Due
- In 2026
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- No publication found by mid-October. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Threat-specific MCM preparedness roadmaps
- Due
- In 2026
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- Now only a "first set โฆ by the end of 2026". Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Launch a European Diagnostics Hub
- Due
- In 2026
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- Launch not confirmed by mid-October. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Launch RAMP UP
- Due
- In 2026
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- Launch not confirmed by mid-October. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Consider revising the Joint Procurement Agreement
- Due
- In 2026
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- HERA will only "contribute to the reflection". Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Launch a study on stockpiling unfinished products
- Due
- In 2026
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Simulation exercise testing the Union plan
- Due
- In 2026
- Committed in
- Union PPR plan, SWD(2025) 393
- Evidence
- No exercise report found by mid-October. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Second round of Member State preparedness reports (Art. 7)
- Due
- 27 Dec 2026
- Committed in
- Regulation (EU) 2022/2371
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
First comprehensive EU risk and threat assessment
- Due
- End 2026
- Committed in
- Preparedness Union Strategy (Mar 2025)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Set minimum preparedness requirements
- Due
- In 2026
- Committed in
- Preparedness Union Strategy (Mar 2025)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Update the threat prioritisation
- Due
- By 2027
- Committed in
- MCM Strategy, Annex 1
- Evidence
- HERA says the exercise continues. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Set up a Therapeutics Hub
- Due
- In 2027
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Expand DURABLE
- Due
- In 2027
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Double HERA Invest to โฌ200 million
- Due
- By 2027
- Committed in
- MCM Strategy (Jul 2025)
- Evidence
- On track according to HERA's own plan. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Set up an EU crisis coordination hub
- Due
- In 2027
- Committed in
- Preparedness Union Strategy (Mar 2025)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- EU FAB expansion and the EU Wastewater Sentinel System (2026): in progress, not coded.
- Indicators to measure the Union plan's performance; Preparedness Union Strategy progress updates: undated.
๐ฉ๐ช Germany Index 0.75 ยท coverage 80% 2 on time1 late1 partial3 not yet due1 unknown
The public-health-service pact (รGD-Pakt) is the best-documented German delivery: its staffing goal was met about two years late. The National Pandemic Plan revision has published no module.
-
On time
Create at least 1,500 permanent public-health posts
- Due
- 31 Dec 2021
- Committed in
- Pact for the Public Health Service (รGD-Pakt, 2020)
- Evidence
- About 2,000 posts by end-2021 (ministry presentation, Mar 2022). Source, 21 Mar 2022 (opens in a new tab)
-
On time
Publish a joint federalโstate interim report on the pact
- Due
- End 2023
- Committed in
- รGD-Pakt
- Evidence
- Interim report dated 12 Dec 2023. Source, 12 Dec 2023 (opens in a new tab)
-
Late
Reach 5,000 new public-health posts in total
- Due
- 31 Dec 2022
- Committed in
- รGD-Pakt
- Evidence
- About 5,210 full-time equivalents by end-2024, about two years late. Source, 4 Jun 2025 (opens in a new tab)
-
Partial
Digitalise local health offices (up to โฌ800m; projects end by 31 Aug 2026)
- Due
- 31 Aug 2026
- Committed in
- รGD-Pakt
- Evidence
- Projects ending "successively"; results not yet reported. Source, 4 Jun 2025 (opens in a new tab)
-
Unknown
Annual pact reports to the Bundestag budget committee
- Due
- Each 1 April to 2026
- Committed in
- รGD-Pakt
- Evidence
- The reports go to the committee and are not routinely public. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Publish the independent evaluation of the digitalisation programme
- Due
- End 2026
- Committed in
- รGD-Pakt
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Publish the pact's final report
- Due
- In 2027
- Committed in
- รGD-Pakt
- Evidence
- Not yet due; federal funding ends 31 Dec 2026. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Final report of the Bundestag COVID inquiry commission (Enquete-Kommission)
- Due
- 30 Jun 2027
- Committed in
- Bundestag decision (Jul 2025)
- Evidence
- No interim report found. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Revision of the National Pandemic Plan (concept of June 2024): no deadline set; no module published; coordinating office extended to end-2029.
๐ซ๐ท France Index n/a (too few items to rank) ยท coverage 0% 2 unknown
The government pandemic plan is a decision aid with undated, unpublished commitments, so delivery cannot be checked. France's only hard deadline is external: the EU action plan answering ECDC's January 2026 assessment.
-
Unknown
Ministries send readiness indicators to the SGDSN
- Due
- Standing
- Committed in
- Plan gouvernemental de rรฉponse ร une pandรฉmie (Mar 2024), p.20
- Evidence
- The indicators are not published. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Submit an action plan answering ECDC's preparedness assessment (EU Art. 8(3))
- Due
- About Oct 2026
- Committed in
- Regulation (EU) 2022/2371; ECDC report (Jan 2026)
- Evidence
- No published plan found; France may have submitted one without publishing it. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Pathogen characteristics the plan says it "will present", climate-related updates and regular exercises: undated.
- Capability dates recorded by ECDC (stockpile information system in 2026, SISACโATHINA link by April 2026): reported by ECDC, not in the plan; no evidence either way.
๐ฎ๐น Italy Index 0.33 ยท coverage 75% 1 late1 partial1 overdue8 not yet due1 unknown
The 2025โ2029 plan arrived about 28 months after its predecessor expired, then set tight dates. Regional money is released only against verified resolutions and reports, a design that is still untested.
-
Late
Adopt a successor to the 2021โ2023 pandemic influenza plan
- Due
- End 2023
- Committed in
- PanFlu 2021โ2023
- Evidence
- The 2025โ2029 plan was agreed on 30 Apr 2026, about 28 months late. Source, 30 Apr 2026 (opens in a new tab)
-
Partial
Regions adopt a resolution with a timetable for the minimum actions within 90 days
- Due
- About 29 Jul 2026
- Committed in
- StateโRegions agreement (Apr 2026), art. 2(3)
- Evidence
- Lombardia, Piemonte and Sicily adopted theirs on time; no national tally exists. Source, 24 Jul 2026 (opens in a new tab)
-
Overdue
Complete the ICU bed build-out (8,679 beds) under DL 34/2020
- Due
- Legacy (2020 programme)
- Committed in
- Decree-Law 34/2020 (legacy commitment)
- Evidence
- The 2025โ2029 plan itself says it is "still under way and not yet completed". Source, 15 Jun 2026 (opens in a new tab)
-
Unknown
Committee checks the regional resolutions within 150 days; the โฌ50m 2025 tranche is released
- Due
- About late Sep 2026
- Committed in
- StateโRegions agreement, art. 2(4)โ(6)
- Evidence
- No committee opinions or transfers found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Regions adopt a second resolution covering the remaining minimum actions
- Due
- About 30 Jan 2027
- Committed in
- StateโRegions agreement, art. 2(7)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Regions file their first activity and financial report
- Due
- 28 Feb 2027
- Committed in
- StateโRegions agreement, art. 2(8)
- Evidence
- An annex gives 30 September instead, an inconsistency in the plan. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Ministry evaluation to the Treasury to release the โฌ150m 2026 tranche
- Due
- 30 Apr 2027
- Committed in
- StateโRegions agreement
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Regions amend health-staff law so plan funds can pay for hires
- Due
- End 2026
- Committed in
- StateโRegions agreement (premises)
- Evidence
- No evidence either way yet. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
One-year national deliverables (care reprioritisation, clinical expert network, points-of-entry plan, blood and transplant measures)
- Due
- About 30 Apr 2027
- Committed in
- Piano strategico-operativo 2025โ2029
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
National exercise within two years; regional exercises within three
- Due
- About Apr 2028 and Apr 2029
- Committed in
- Piano strategico-operativo 2025โ2029, pp.131โ132
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Two-yearly stockpile-management monitoring report and pathogen-list review
- Due
- About 2028
- Committed in
- Piano strategico-operativo 2025โ2029
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Evaluate regional preparedness with 33 indicators
- Due
- Within the cycle to 2029
- Committed in
- Piano strategico-operativo 2025โ2029, pp.129โ130
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Public health emergency operations centre (PHEOC): to be set up by legal acts, no date; "not active" at adoption.
๐ช๐ธ Spain Index 0.30 ยท coverage 100% 1 on time1 late3 overdue2 not yet due
The law creating the public health agency passed, but its statute and the royal decree approving the state preparedness plan are overdue. Both are now promised "before the end of 2026".
-
On time
Create the State Public Health Agency (AESAP) by law
- Due
- No fixed date
- Committed in
- Government commitment
- Evidence
- Ley 7/2025 of 28 Jul 2025, after an initial defeat in Congress. Source, 28 Jul 2025 (opens in a new tab)
-
Late
Submit an action plan answering ECDC's preparedness assessment (EU Art. 8(3))
- Due
- About Apr 2026
- Committed in
- Regulation (EU) 2022/2371; ECDC report (Jul 2025)
- Evidence
- Plan dated 8 Jun 2026, about two months late. Source, 8 Jun 2026 (opens in a new tab)
-
Overdue
Approve the state preparedness plan (Plan Estatal) by royal decree
- Due
- In 2024, then 2025
- Committed in
- Annual regulatory plans 2024 and 2025
- Evidence
- Still unapproved in Aug 2026; now promised "before the end of 2026". Source, 11 Aug 2026 (opens in a new tab)
-
Overdue
Adopt the AESAP statute within six months of the law
- Due
- About Feb 2026
- Committed in
- Ley 7/2025
- Evidence
- No statute in the official gazette by 16 Oct 2026; re-promised for year-end. Source, 8 May 2026 (opens in a new tab)
-
Overdue
Review the 2005 influenza plan periodically
- Due
- Periodic
- Committed in
- Plan Nacional de Preparaciรณn y Respuesta ante una Pandemia de Gripe (2005)
- Evidence
- Last known update December 2006. Source, 1 Dec 2006 (opens in a new tab)
-
Not yet due
Carry out the action-plan items (risk prioritisation, incident management, risk communication and others)
- Due
- 2026โ28
- Committed in
- Spain PHEPA Action Plan (Jun 2026)
- Evidence
- Self-reported: many marked "NO INICIADO" (not started). Source, 8 Jun 2026 (opens in a new tab)
-
Not yet due
Indicators and regional plans within one year; three-yearly public report
- Due
- One year after adoption
- Committed in
- Draft royal decree (Sep 2025)
- Evidence
- Conditional on the decree, which is not adopted. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Congress "Conclusions for Reconstruction" (July 2020): emergency plan, strategic reserve, rapid response teams; not dated, still not delivered.
Nordic and Alpine Europe
๐ธ๐ช Sweden Index 1.00 (too few items to rank) ยท coverage 100% 2 on time2 not yet due
The government's single dated commitment is a restrictions law in force on 1 April 2027, on track. No pandemic strategy has been adopted and none has been dated.
-
On time
Inquiry delivers the basis for a national pandemic strategy (interim report)
- Due
- Apr 2025
- Committed in
- Committee directive Dir. 2023:106
- Evidence
- SOU 2025:48 published April 2025. Source, 1 Apr 2025 (opens in a new tab)
-
On time
Inquiry final report
- Due
- Apr 2026
- Committed in
- Committee directive Dir. 2023:106 (amended)
- Evidence
- SOU 2026:25 published 2 Apr 2026. Source, 2 Apr 2026 (opens in a new tab)
-
Not yet due
New law on special restrictions to stop infection spreading
- Due
- 1 Apr 2027
- Committed in
- Government press release and Lagrรฅdsremiss (Aug 2026)
- Evidence
- On track: Lagrรฅdsremiss signed 20 Aug 2026. Source, 26 Aug 2026 (opens in a new tab)
-
Not yet due
Final inquiry proposals (disease classification, infection-control coordination)
- Due
- 1 Jul 2027
- Committed in
- SOU 2026:25
- Evidence
- No bill found yet. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Adoption of a national pandemic strategy: no date set by the government.
- Two government assignments proposed by the inquiry (rule mapping; risk-group planning support): not committed, no evidence of issue.
๐ซ๐ฎ Finland Index 1.00 (too few items to rank) ยท coverage 33% 2 on time4 unknown
The 2024 plan sets no dates of its own, so the checkable items come from the EU assessment cycle. No update adding ECDC's recommendations was found.
-
On time
Replace the 2012 pandemic plan after consultation
- Due
- After the 2023 consultation
- Committed in
- Ministry of Social Affairs and Health (consultation 2023)
- Evidence
- Plan published 12 Apr 2024 (English edition 19 Jun 2024). Source, 12 Apr 2024 (opens in a new tab)
-
On time
Submit an action plan answering ECDC's preparedness assessment (EU Art. 8(3))
- Due
- About Sep 2026
- Committed in
- Regulation (EU) 2022/2371; ECDC report (Dec 2025)
- Evidence
- ECDC links an "Action plan from Finland"; its content could not be read. Source, 1 Apr 2026 (opens in a new tab)
-
Unknown
Update the plan "as necessary"
- Due
- No interval
- Committed in
- Pandemic Preparedness Plan (2024), p.12
- Evidence
- No 2025โ26 revision found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Add a laboratory surge strategy and sentinel respiratory reporting to the plan
- Due
- Via the action plan
- Committed in
- ECDC recommendation (Dec 2025), via the action plan
- Evidence
- No updated plan found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Reflect the Zoonosis Centre's role and IHR travel principles in the plan
- Due
- Via the action plan
- Committed in
- ECDC recommendation (Dec 2025), via the action plan
- Evidence
- No updated plan found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Health-sector risk and vulnerability analysis
- Due
- Via the action plan
- Committed in
- ECDC recommendation (Dec 2025), via the action plan
- Evidence
- No evidence found. Source, 16 Oct 2026 (opens in a new tab)
๐ณ๐ด Norway Index 0.50 ยท coverage 100% 1 on time3 partial1 overdue1 not yet due
An updated national health preparedness plan and a permanent PPE stockpile model are in place. The new infectious-disease and preparedness laws have not reached the Storting a year after the minister said they were being finalised.
-
On time
Update the National Health Preparedness Plan
- Due
- In 2025
- Committed in
- Government
- Evidence
- Updated plan published May 2025. Source, 1 May 2025 (opens in a new tab)
-
Partial
Review crisis and preparedness laws and add children's best interests (Storting resolution)
- Due
- Not dated
- Committed in
- Storting resolution, Innst. 151 S (Mar 2025)
- Evidence
- The consultation draft adds a child best-interest assessment; the laws are not yet passed. Source, 8 Apr 2026 (opens in a new tab)
-
Partial
Permanent national PPE stockpile of about six months' pandemic use
- Due
- Standing
- Committed in
- Health ministry tasking (Jan 2024)
- Evidence
- Stockpile model set up; its fill level is not reported. Source, 26 May 2025 (opens in a new tab)
-
Partial
Plan for up to 1,200 ICU beds and more ICU-nurse training places
- Due
- Standing
- Committed in
- Government
- Evidence
- Training places "more than doubled" since 2020 (minister's claim). Source, 26 May 2025 (opens in a new tab)
-
Overdue
New infectious-disease and health-preparedness laws
- Due
- Not dated
- Committed in
- Minister's answer to Parliament (May 2025: "about to finalise")
- Evidence
- Consultation closed 8 Apr 2026; no bill in the Storting by 16 Oct 2026. Source, 8 Apr 2026 (opens in a new tab)
-
Not yet due
Grow Civil Defence conscripts from 8,000 to 12,000
- Due
- Over eight years (about 2033)
- Committed in
- Government
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- New "Pandemiplanen" (commissioned 2024): no public date; still in drafting.
๐ฉ๐ฐ Denmark Index 0.80 ยท coverage 100% 3 on time2 partial3 not yet due
The strategy is reviewed "continuously" and makes almost no dated commitments. The checkable items come from the national audit office's follow-up and from related stockpile laws, which were delivered on time.
-
On time
Update preparedness guidance and the pandemic plan to reflect the national risk picture
- Due
- Audit follow-up
- Committed in
- Minister's response to audit report 18/2021
- Evidence
- Audit office closed the point on 22 Jan 2025 after the January 2025 strategy. Source, 22 Jan 2025 (opens in a new tab)
-
On time
State preparedness for medical devices
- Due
- 1 Jan 2026
- Committed in
- Amendment to the Medical Devices Act (Dec 2025)
- Evidence
- Established as of 1 Jan 2026. Source, 2 Jan 2026 (opens in a new tab)
-
On time
Mandatory stocks of critical medicines
- Due
- 1 Jul 2024
- Committed in
- Law of 4 Jun 2024
- Evidence
- In force 1 Jul 2024; new list in force 1 Jul 2026. Source, 1 Jul 2024 (opens in a new tab)
-
Partial
Four regions adopt new preparedness plans
- Due
- In 2025
- Committed in
- Audit follow-up note RN 401/25
- Evidence
- Evidence found for one region (Midtjylland) only. Source, 16 Oct 2026 (opens in a new tab)
-
Partial
Regional PPE stocks meet national target figures
- Due
- Standing
- Committed in
- 2023 governmentโregions stockpile model
- Evidence
- Targets met for 6 of 7 items in early 2025. Source, 22 Jan 2025 (opens in a new tab)
-
Not yet due
Capital Region adopts a new plan before Region รstdanmark is created
- Due
- In 2027
- Committed in
- Audit follow-up note RN 401/25
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Audit office continues to follow regional plans and PPE
- Due
- Next note not dated
- Committed in
- Audit follow-up note RN 401/25
- Evidence
- No 2026 follow-up note found yet. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Evaluate the critical-medicines stock law
- Due
- Before 1 Jan 2027
- Committed in
- Law of 4 Jun 2024
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Continuous ("lรธbende") review of the strategy: no date, uncheckable.
๐ฆ๐น Austria Index 0.30 ยท coverage 83% 3 partial2 overdue1 not yet due1 unknown
The new Epidemic Act, promised as a draft by year-end in 2022โ23, had still not reached formal consultation in September 2026. The Court of Audit's follow-ups record most other pandemic recommendations as only "promised".
-
Partial
New general pandemic plan for known and unknown pathogens, with the states
- Due
- As soon as possible
- Committed in
- Court of Audit report 2022/18, Rec. 10
- Evidence
- Ministry self-reports "implemented"; no joint federalโstate plan found. Source, 1 Dec 2024 (opens in a new tab)
-
Partial
Act on the Court of Audit's COVID-testing recommendations
- Due
- Follow-up 2024
- Committed in
- Court of Audit report Bund 2023/19
- Evidence
- One recommendation partly implemented; most only "promised". Source, 1 Dec 2024 (opens in a new tab)
-
Partial
Take the April 2023 audit recommendations into the 2023 plan
- Due
- In 2023
- Committed in
- Pandemic plan for respiratory diseases (2023), p.6
- Evidence
- Key items (vaccination responsibility, IHR rules) remain open. Source, 1 Apr 2023 (opens in a new tab)
-
Overdue
Draft a new Epidemic Act
- Due
- By year-end (2022โ23)
- Committed in
- Minister's announcement (Sep 2022); 2023 plan
- Evidence
- Still not in formal consultation in Sep 2026, about three years overdue. Source, 8 Sep 2026 (opens in a new tab)
-
Overdue
Settle who is responsible for, and pays for, pandemic vaccination
- Due
- Audit follow-up
- Committed in
- Court of Audit reports 2022/18 and 2023/1
- Evidence
- Recorded as "not implemented" in the 2023 and 2024 follow-ups. Source, 1 Dec 2024 (opens in a new tab)
-
Unknown
IHR implementing rules and a legal duty for electronic reporting
- Due
- Audit follow-up
- Committed in
- Court of Audit report 2023/1, Recs. 37โ39
- Evidence
- Recorded only as "promised"; no delivery evidence. Source, 1 Dec 2024 (opens in a new tab)
-
Not yet due
Complete the epidemic-law reform
- Due
- Within the term (about 2029)
- Committed in
- Coalition programme (2025)
- Evidence
- A related opposition motion was postponed in June 2026. Source, 23 Jun 2026 (opens in a new tab)
๐จ๐ญ Switzerland Index 0.83 ยท coverage 75% 2 on time1 partial4 not yet due1 unknown
The plan was published on 1 July 2025 as decided, and its first update arrived on 10 September 2026, ahead of the default two-year cycle. Capacity commitments are deferred to 2027 or later.
-
On time
Publish the pandemic plan
- Due
- Mid-2025
- Committed in
- Steering group decision
- Evidence
- Published 1 Jul 2025. Source, 1 Jul 2025 (opens in a new tab)
-
On time
Work second-reading feedback into the plan
- Due
- In 2026
- Committed in
- Pandemic Plan consultation report (2025)
- Evidence
- First update published 10 Sep 2026 (the link to the feedback is inferred). Source, 10 Sep 2026 (opens in a new tab)
-
Partial
Governed update cycle: two-yearly updates, 60-day consultation, annual steering decision
- Due
- Annual decision
- Committed in
- Pandemic Plan, update rules
- Evidence
- Update arrived early; no consultation record or decision minutes found. Source, 10 Sep 2026 (opens in a new tab)
-
Unknown
Keep PPE stocks for at least 12 weeks of pandemic demand
- Due
- Standing
- Committed in
- Pandemic Plan (recommendation)
- Evidence
- Not monitored; no federal legal basis for stockpiling. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Revised Epidemics Act in force
- Due
- 2027 or 2028
- Committed in
- Federal Council message (Aug 2025)
- Evidence
- On track: Council of States passed it 39โ3 on 22 Sep 2026. Source, 22 Sep 2026 (opens in a new tab)
-
Not yet due
Clarify supply-security responsibilities, financing and processes
- Due
- End 2027
- Committed in
- Federal Council decision (21 Aug 2024)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Comprehensive plan update when the revised Act enters into force
- Due
- After 2027/28
- Committed in
- Pandemic Plan, update rules
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Decide on joining the WHO Pandemic Agreement once its annex is agreed
- Due
- Conditional
- Committed in
- Pandemic Plan, global context (Sep 2026)
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Emerging economies
๐น๐ญ Thailand Index 1.00 (too few items to rank) ยท coverage 33% 2 on time3 not yet due4 unknown
Annual WHO SPAR reporting is the only public evidence, and the score is rising. The plan's quarterly KPI reports and executive committee leave no public trace.
-
On time
Report annually to WHO (SPAR)
- Due
- Annual
- Committed in
- NAPHS 2023โ2027, p.43
- Evidence
- Filed every year: 87 (2023), 89 (2024), 91 (2025). Source, 4 May 2026 (opens in a new tab)
-
On time
WHO certification of the national Emergency Medical Team (Type 2)
- Due
- In 2024
- Committed in
- NAPHS 2023โ2027, p.127
- Evidence
- Stated in the plan; not independently verified. Source, 1 Jan 2024 (opens in a new tab)
-
Unknown
Quarterly monitoring of projects and KPIs
- Due
- Quarterly from 2023
- Committed in
- NAPHS 2023โ2027, p.189
- Evidence
- No progress report found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Appoint an executive committee
- Due
- About 2023
- Committed in
- NAPHS 2023โ2027, p.188
- Evidence
- No appointment order found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Review and improve lessons learned annually
- Due
- Annual
- Committed in
- NAPHS 2023โ2027, p.44
- Evidence
- No after-action or lessons report found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Spend the project budgets (about 16.7bn baht)
- Due
- 2023โ27
- Committed in
- NAPHS 2023โ2027
- Evidence
- No execution data found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Cost future pandemic preparedness (5m baht study)
- Due
- By 2027
- Committed in
- NAPHS 2023โ2027, p.88
- Evidence
- No output found yet. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
SPAR guideline and two assessments before a JEE
- Due
- In 2030
- Committed in
- NAPHS 2023โ2027, p.186
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Points of entry at level 5 on all indicators
- Due
- In 2030
- Committed in
- NAPHS 2023โ2027, p.41
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
๐ฎ๐ฉ Indonesia Index 0.75 (too few items to rank) ยท coverage 50% 1 on time1 late5 not yet due2 unknown
The plan is about 10 months old, so most targets point to a JEE in 2028 and level distributions in 2029. The Pandemic Fund grant started a year later than the plan assumed.
-
On time
Self-assess annually with WHO SPAR
- Due
- Annual
- Committed in
- NAPHS 2025โ2029
- Evidence
- Filed: 80 (2024), 80 (2025). Source, 4 May 2026 (opens in a new tab)
-
Late
Start the Pandemic Fund grant (CARE-I)
- Due
- In 2025
- Committed in
- NAPHS 2025โ2029, p.28
- Evidence
- Runs 2026โ2028; launched 15โ16 Apr 2026. Source, 20 Apr 2026 (opens in a new tab)
-
Unknown
Help establish a National IHR Authority
- Due
- Not dated
- Committed in
- NAPHS 2025โ2029, p.vi
- Evidence
- No designation found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Fund and spend the Rp46.58 trillion plan budget
- Due
- 2025โ29
- Committed in
- NAPHS 2025โ2029, ch. VII
- Evidence
- No execution data found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
CARE-I outputs: One Health surveillance network and guidelines, risk-communication update, simulation exercise
- Due
- 2026โ28
- Committed in
- Pandemic Fund project
- Evidence
- No milestone reports after the launch. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
JEE-linked workforce items (4,000 infection-control nurses; 100 cadres per health centre a year)
- Due
- Within 2โ5 years
- Committed in
- NAPHS 2025โ2029, pp.82โ85
- Evidence
- No tracking found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Hold a Joint External Evaluation
- Due
- In 2028
- Committed in
- NAPHS 2025โ2029, p.37
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Reach the 2029 JEE target distribution (42 indicators at level 4, 11 at level 5)
- Due
- In 2029
- Committed in
- NAPHS 2025โ2029, p.111
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Evaluate this plan and develop NAPHS 2030โ2034
- Due
- About 2028โ29
- Committed in
- NAPHS 2025โ2029, p.37
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Implementing regulation of Health Law 17/2023 (PP 28/2024): delivered in 2024, before the plan.
๐ณ๐ฌ Nigeria Index 0.69 ยท coverage 80% 3 on time1 late4 partial2 unknown
Recurring WHO reporting is on time. The successor plan, NAPHS 2.0, was "unveiled" in November 2025 but is still "pending ministerial assent" three years after the first plan expired.
-
On time
Hold periodic Joint External Evaluations
- Due
- About every five years
- Committed in
- NAPHS 2018โ2022, p.19
- Evidence
- Second JEE in Aug 2023; score 39% โ 54%. Source, 18 Aug 2023 (opens in a new tab)
-
On time
Report annually to WHO (SPAR)
- Due
- Annual
- Committed in
- NAPHS 2018โ2022, p.19
- Evidence
- Filed 2021โ2025: 63, 56, 61, 57, 60. Source, 4 May 2026 (opens in a new tab)
-
On time
Adopt the 7-1-7 timeliness target
- Due
- Not dated
- Committed in
- NCDC
- Evidence
- In use in rapid-response reports and training (NCDC 2025 report). Source, 2 Jun 2026 (opens in a new tab)
-
Late
Review the expired plan
- Due
- 2022/23
- Committed in
- NAPHS 2018โ2022
- Evidence
- End-term review completed November 2024. Source, 30 Nov 2024 (opens in a new tab)
-
Partial
One Health medical-countermeasures stockpile
- Due
- By 2021
- Committed in
- NAPHS 2018โ2022, p.11
- Evidence
- A strategic stockpile function exists; its scope and size are not stated. Source, 2 Jun 2026 (opens in a new tab)
-
Partial
Develop and adopt NAPHS 2.0
- Due
- 2023/24
- Committed in
- NAPHS 2018โ2022 successor process
- Evidence
- "Unveiled" Nov 2025 but "pending ministerial assent"; text not public. Source, 2 Jun 2026 (opens in a new tab)
-
Partial
Annual operational plans
- Due
- Annual
- Committed in
- NAPHS
- Evidence
- State-level plans exist; no national NAPHS 2.0 plan found. Source, 31 Jul 2026 (opens in a new tab)
-
Partial
Subnational evaluations and state action plans for health security
- Due
- Ongoing
- Committed in
- NAPHS
- Evidence
- Only 19% of states can do joint risk assessment. Source, 2 Jun 2026 (opens in a new tab)
-
Unknown
Federal Executive Council approval of the 2018 plan
- Due
- In 2018
- Committed in
- NAPHS 2018โ2022, p.18
- Evidence
- No approval record found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Extend surveillance to 80% of private health facilities
- Due
- By 2021
- Committed in
- NAPHS 2018โ2022, p.45
- Evidence
- No measured figure found. Source, 16 Oct 2026 (opens in a new tab)
๐ฎ๐ณ India Index 0.22 ยท coverage 43% 1 on time2 partial6 overdue12 unknown
All 20 NITI Aayog "key steps" fell due by about September 2026. No evidence was found of the headline governance items; delivery runs through the One Health Mission instead. The report is advisory, so these are advisory timelines.
-
On time
Report annually to WHO (SPAR)
- Due
- Annual
- Committed in
- IHR (2005)
- Evidence
- Filed: 86 (2023), 88 (2024), 88 (2025). Source, 4 May 2026 (opens in a new tab)
-
Partial
Operationalise a One Health institute
- Due
- 3โ6 months (about Mar 2025)
- Committed in
- NITI Aayog Expert Group framework (Aug 2024), p.58
- Evidence
- The National Institute of One Health is still "being set up" in Nagpur (Nov 2025). Source, 20 Nov 2025 (opens in a new tab)
-
Partial
National biosecurity biorepository network
- Due
- 12โ24 months (about Sep 2026)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- A BSL-3/4 lab network (22โ23 labs) exists under the One Health Mission; not a biorepository. Source, 1 Dec 2025 (opens in a new tab)
-
Overdue
Set up an Empowered Group of Secretaries for pandemic preparedness
- Due
- 3โ6 months (about Mar 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No publication foundNo publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Overdue
Approve a special pandemic preparedness and response (PPER) fund
- Due
- 3โ6 months (about Mar 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No publication foundNo publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Overdue
Framework for monitoring targets with a scorecard
- Due
- 3โ6 months (about Mar 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No publication foundNo publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Overdue
Vaccine science and development institute
- Due
- 6โ12 months (about Sep 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No publication foundNo publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Overdue
Approve a Public Health Emergency Management Act
- Due
- 12โ24 months (about Sep 2026)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No bill has been introduced. Source, 16 Oct 2026 (opens in a new tab)
-
Overdue
Mission on therapeutics and drug development
- Due
- 12โ24 months (about Sep 2026)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No publication foundNo publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Institutionalise genomic surveillance (INSACOG) with an SOP for regional expansion
- Due
- 3โ6 months (about Mar 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- INSACOG pre-exists (2020); no new SOP found. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
SOP for data sharing and risk communication
- Due
- 3โ6 months (about Mar 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Nationwide capacity-building roadmap
- Due
- 3โ6 months (about Mar 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Engage states and ministries
- Due
- 6โ12 months (about Sep 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Collaboration framework and memorandums of understanding
- Due
- 6โ12 months (about Sep 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Integrate ICMR and NCDC data portals
- Due
- 6โ12 months (about Sep 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
High-risk innovation research fund
- Due
- 6โ12 months (about Sep 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- Not found; a general national R&D fund may be relevant. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Priority-pathogen research through a network of centres of excellence
- Due
- 6โ12 months (about Sep 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Regional surveillance consortium with neighbours
- Due
- 6โ12 months (about Sep 2025)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Epidemiological forecasting and modelling network
- Due
- 12โ24 months (about Sep 2026)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Regulatory autonomy and emergency use authorisation SOPs
- Due
- 12โ24 months (about Sep 2026)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Capacity-building programme at all levels
- Due
- 12โ24 months (about Sep 2026)
- Committed in
- NITI Aayog framework, p.58
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
Not counted (no deadline, not itemised or claimed only)
- Participation in a WHO JEE or UHPR peer review: undated, not evidenced.
๐ง๐ท Brazil Index 0.60 ยท coverage 83% 2 on time2 partial1 overdue2 not yet due1 unknown
The respiratory-virus pandemic plan, due by July 2026, has not appeared; states were asked for contingency plans instead.
-
On time
Set up a situation room for respiratory viruses
- Due
- In 2025
- Committed in
- Diretrizes for COVID-19, influenza and other respiratory viruses (2025)
- Evidence
- Created June 2025, including avian influenza. Source, 1 Jun 2025 (opens in a new tab)
-
On time
Report annually to WHO (SPAR)
- Due
- Annual
- Committed in
- IHR (2005)
- Evidence
- Filed: 75 (2023), 65 (2024), 70 (2025). Source, 4 May 2026 (opens in a new tab)
-
Partial
Run a simulation exercise linked to the national contingency plan, with an evaluation report
- Due
- Jul 2026
- Committed in
- Diretrizes (2025), p.36
- Evidence
- Exercise held May 2026; the promised evaluation report has not been seen. Source, 5 May 2026 (opens in a new tab)
-
Partial
Update the national avian influenza contingency plan
- Due
- In 2025
- Committed in
- Diretrizes (2025), pp.34, 36
- Evidence
- Revised edition January 2025; a further revision under way in May 2026. Source, 1 Jan 2025 (opens in a new tab)
-
Overdue
Draft or update the national respiratory-virus pandemic plan
- Due
- Jul 2026
- Committed in
- Diretrizes (2025), p.36
- Evidence
- No publication foundStates were asked for contingency plans instead (NT 87/2026). No publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Research prioritisation report
- Due
- Dec 2025
- Committed in
- Diretrizes (2025), p.32
- Evidence
- Not found. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Long-term Diretrizes actions
- Due
- Jul 2027
- Committed in
- Diretrizes (2025), p.12
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
-
Not yet due
Add at least one new vaccination technology or extended use
- Due
- By 2030
- Committed in
- Diretrizes (2025), p.17
- Evidence
- Not yet due. Source, 16 Oct 2026 (opens in a new tab)
๐ฎ๐ฑ Israel Index 0.50 ยท coverage 71% 2 on time1 partial2 overdue2 unknown
Recurring operational instruments (winter circulars, SPAR) are delivered. The revision of the national pandemic plan, due at the end of 2023, shows no evidence of completion.
-
On time
Issue the annual winter-preparedness circular (2025โ26)
- Due
- Before winter 2025
- Committed in
- Ministry of Health
- Evidence
- Circular 8/2025 issued 26 Oct 2025. Source, 26 Oct 2025 (opens in a new tab)
-
On time
Report annually to WHO (SPAR)
- Due
- Annual
- Committed in
- IHR (2005)
- Evidence
- Filed 2022โ2025, score 86 each year. Source, 4 May 2026 (opens in a new tab)
-
Partial
Issue winter guidance for 2026โ27
- Due
- Before winter 2026
- Committed in
- Ministry of Health
- Evidence
- News reports say guidance went to hospitals in Sep 2026; no circular published yet. Source, 14 Sep 2026 (opens in a new tab)
-
Overdue
Update the national pandemic plan (Nachshol Bari) scenario and concept
- Due
- End 2023
- Committed in
- State Comptroller report (May 2024)
- Evidence
- No publication foundNo publication found as of 16 Oct 2026 (absence of evidence, not proof). Source, 16 Oct 2026 (opens in a new tab)
-
Overdue
Keep antivirals for 25% of the population
- Due
- Standing
- Committed in
- National target (2005)
- Evidence
- Last audited at 16% (2020); no newer figure. Source, 1 Oct 2020 (opens in a new tab)
-
Unknown
Prepare and rehearse an operational influenza-pandemic plan (Ministry of Health and health funds)
- Due
- After 2020
- Committed in
- State Comptroller report (2020)
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
-
Unknown
Education ministry interim pandemic plan until Nachshol Bari is updated
- Due
- After 2024
- Committed in
- State Comptroller report (May 2024)
- Evidence
- No evidence either way. Source, 16 Oct 2026 (opens in a new tab)
Watch list: upcoming deadlines
The next nine months carry far more deadlines than the past two years. The single most informative date is 31 March 2027, when the UK's 16 short-term actions, New Zealand's March actions and Canada's fiscal-year commitments converge; with New Zealand's 30 June 2027 cluster they add roughly 45 items. Dates given only as a year are read as its last day.
Due now (October 2026) (4)
-
About late Sep 2026๐ฎ๐น Italy
Coordination Committee 150-day check; โฌ50m 2025 tranche
Status now: Unverified ยท GU S.O. 25/2026 (opens in a new tab)
-
About Oct 2026๐ฆ๐บ Australia
CDC first annual report (2025โ26)
Status now: Not found ยท Bills Digest (opens in a new tab)
-
About Oct 2026๐ซ๐ท France
EU Art. 8(3) action plan answering ECDC's January 2026 assessment
Status now: Not found ยท ECDC PHEPA France (opens in a new tab)
-
Oct 2026๐ธ๐ช Sweden
Bill to Parliament after the Council on Legislation (opinion possibly 1 Oct)
Status now: Not yet tabled ยท Government press release (opens in a new tab)
November 2026 (2)
-
Nov 2026๐ฐ๐ท South Korea
4th national infectious-disease R&D strategy (2027โ31)
Status now: Pending ยท KDCA work report (opens in a new tab)
-
End Nov 2026๐ฌ๐ง United Kingdom
Scotland: combined Module 1 and 2 Inquiry update
Status now: Pending ยท gov.scot (opens in a new tab)
December 2026 (9)
-
27 Dec 2026 / end-2026๐ช๐บ European Union
EU List of MCMs; first roadmaps; Diagnostics Hub; RAMP UP; Union-plan exercise; minimum preparedness requirements; first EU risk and threat assessment; Art. 7 reporting round; end of first ECDC cycle
Status now: None evidenced by mid-October ยท HERA work plan 2026; COM(2025) 745 (opens in a new tab)
-
Before 1 Jan 2027๐ฉ๐ฐ Denmark
Evaluation of the critical-medicines stock law
Status now: Pending ยท Lov 2024/650 (opens in a new tab)
-
31 Dec 2026๐ฉ๐ช Germany
Pact digitalisation evaluation results; pact expiry; reported (unverified) year-end target for the pandemic plan
Status now: Pending ยท BT-Drs. 21/416 (opens in a new tab)
-
End-2026๐ฎ๐น Italy
Regions' health-staff law amendments
Status now: Unknown ยท GU S.O. 25/2026 (opens in a new tab)
-
31 Dec 2026๐ณ๐ฟ New Zealand
Actions 2.5, 3.2, 5.3 and 5.4
Status now: Two not started at publication ยท NZ Government Response, Annex 2 (opens in a new tab)
-
Dec 2026๐ฐ๐ท South Korea
Bed-governance unification; five-syndrome assay; separate crisis fund; KoreaโChinaโJapan forum; mRNA first dosing
Status now: Fund shows no evidence ยท KDCA work report (opens in a new tab)
-
End-2026๐ช๐ธ Spain
Royal decree for the state plan; public health agency statute (both re-promised)
Status now: Overdue against original dates ยท Gaceta Mรฉdica (opens in a new tab)
-
Winter / end-2026๐ฌ๐ง United Kingdom
Exercise Pegasus report; non-respiratory plan adaptation; Module 2 Recs 3, 4 and 17
Status now: No publication yet ยท UK strategy; Module 2 response (opens in a new tab)
-
31 Dec 2026๐บ๐ธ United States
Extended PAHPA provisions expire
Status now: No reauthorisation bill ยท ASTHO (opens in a new tab)
Q1 2027 (JanuaryโMarch) (5)
-
About 30 Jan 2027๐ฎ๐น Italy
Second regional resolutions
Status now: Not yet due ยท GU S.O. 25/2026 (opens in a new tab)
-
28 Feb 2027๐ฎ๐น Italy
First regional activity and financial report
Status now: Not yet due ยท GU S.O. 25/2026 (opens in a new tab)
-
FY2026โ27 (31 Mar 2027)๐จ๐ฆ Canada
Finalise and publish the plan; antiviral and national stockpile recommendations
Status now: Core content only ยท PHAC Departmental Plan 2026โ27 (opens in a new tab)
-
31 Mar 2027๐ณ๐ฟ New Zealand
Actions 4.4 and 7.4
Status now: Pending ยท NZ Government Response, Annex 2 (opens in a new tab)
-
Mar 2027๐ฌ๐ง United Kingdom
16 short-term actions, including the draft All Pandemic Hazards Bill; Civil Contingencies Act post-implementation review
Status now: No public progress ยท UK strategy, pp.62โ67 (opens in a new tab)
AprilโMay 2027 (2)
-
1 Apr 2027๐ธ๐ช Sweden
Restrictions law in force
Status now: On track ยท Government press release (opens in a new tab)
-
About 30 Apr 2027๐ฎ๐น Italy
Treasury evaluation for the โฌ150m 2026 tranche; one-year national deliverables
Status now: Pending ยท GU S.O. 25/2026 (opens in a new tab)
June 2027 (2)
-
30 Jun 2027๐ฉ๐ช Germany
Bundestag COVID inquiry commission final report
Status now: No interim report ยท Bundestag (opens in a new tab)
-
30 Jun 2027๐ณ๐ฟ New Zealand
20 actions, including the strategic framework and all-of-government plan, exercise programme and modelling
Status now: 10 of 32 not started at publication ยท NZ Government Response, Annex 2 (opens in a new tab)
JulyโDecember 2027 (7)
-
Jul 2027๐ง๐ท Brazil
Long-term Diretrizes actions
Status now: Medium-term plan already overdue ยท Diretrizes (2025) (opens in a new tab)
-
About Jul 2027 โ 2028๐จ๐ญ Switzerland
First regular two-yearly update; supply-security clarification (end-2027); revised Epidemics Act in force 2027/28
Status now: Early update done ยท pandemieplan.admin.ch (opens in a new tab)
-
About Oct 2027๐บ๐ธ United States
Two novel antivirals approved; HHS influenza plan horizon ends
Status now: No tracking ยท NBS-IP (opens in a new tab)
-
Throughout 2027๐จ๐ฆ Canada
Technical components of the pandemic plan
Status now: Pending ยท PHAC (opens in a new tab)
-
In 2027๐ช๐บ European Union
Threat-prioritisation update; Therapeutics Hub; DURABLE; crisis coordination hub; HERA Invest โฌ200m
Status now: HERA Invest on track per plan ยท HERA work plan 2026 (opens in a new tab)
-
By 2027๐ฐ๐ท South Korea
Influenza plan: 1,000 sentinel sites and stock targets
Status now: Sentinel sites at 800 ยท KDCA (opens in a new tab)
-
In 2027๐น๐ผ Taiwan
2027 KPIs and regional drills
Status now: Pending ยท TW 2022โ2027 plan (opens in a new tab)
2028โ30 (8)
-
About Apr 2028๐ฎ๐น Italy
National exercise testing the three networks
Status now: Not testable yet ยท GU S.O. 25/2026 (opens in a new tab)
-
2028 onward๐จ๐ฆ Canada
Pandemic vaccine readiness agreements
Status now: Request for information done ยท PHAC Departmental Plan 2026โ27 (opens in a new tab)
-
In 2028๐ฎ๐ฉ Indonesia
Joint External Evaluation
Status now: Not testable yet ยท ID NAPHS (opens in a new tab)
-
In 2028๐ฐ๐ท South Korea
Domestic mRNA vaccine licensed
Status now: At risk ยท Dailypharm (opens in a new tab)
-
In 2028๐ฌ๐ง United Kingdom
Strategy review
Status now: Not testable yet ยท UK strategy, p.67 (opens in a new tab)
-
FY2028๐ฏ๐ต Japan
Dual-use vaccine manufacturing sites
Status now: Construction under way ยท FY2025 follow-up (opens in a new tab)
-
About 2030๐ฏ๐ต Japan
Action Plan revision
Status now: Not testable yet ยท FY2025 follow-up (opens in a new tab)
-
In 2030๐น๐ญ Thailand
Joint External Evaluation; points of entry at level 5
Status now: Not testable yet ยท TH NAPHS (opens in a new tab)
Who reports on delivery
Most jurisdictions either publish without judging delivery, or judge without publishing. Only New Zealand's action table, Taiwan's KPI annex and Spain's status column state item by item whether a dated commitment was met, and Denmark's audit office is the only independent body that explicitly closes items.
| Jurisdiction | Mechanism | Publishes? | Judges delivery item by item? | Independent? |
|---|---|---|---|---|
| ๐ฌ๐ง United Kingdom | Biological Security Strategy annual report; Inquiry six-monthly updates; "existing mechanisms" plus a 2028 review | BSS yes (Jul 2025, Jul 2026); Inquiry updates lapsed after Jul 2025 | No ratings | No |
| ๐บ๐ธ United States | Internal National Security Council tracking; global health security annual report | No; last report covered FY2022 | No | No |
| ๐จ๐ฆ Canada | Departmental Plans and Results Reports | Yes (generic) | Partly | No |
| ๐ฆ๐บ Australia | CDC annual report to Parliament (statutory) | First not yet found | No | No |
| ๐ณ๐ฟ New Zealand | Annex 2 action table; Ministry "periodic updates" | Table yes; no updates yet | Yes (status per action) | No |
| ๐ฏ๐ต Japan | Annual follow-up to the Promotion Council | Yes, on time | Only for four numeric targets | No |
| ๐ฐ๐ท South Korea | Quarterly and half-yearly internal checks; Board of Audit and Inspection | Checks no; audit yes | Internally only | Audit yes |
| ๐น๐ผ Taiwan | Annual KPI results annex | Yes, one year late; 2025 not found | Yes | No |
| ๐ธ๐ฌ Singapore | None | โ | โ | โ |
| ๐ช๐บ European Union | Reg. 2022/2371 Arts. 7โ9 cycle; ECDC assessments; HERA work plan; Preparedness Union "updates" | Cycle and ECDC yes; HERA forward-looking; no written Union report | Partly | ECDC yes |
| ๐ฉ๐ช Germany | Pact interim report; budget-committee reports; federal audit office | Interim yes; committee reports no | Partly | Audit office yes |
| ๐ซ๐ท France | Ministry indicators to the SGDSN; ECDC assessment | Indicators no; ECDC yes | No | ECDC yes |
| ๐ฎ๐น Italy | Coordination Committee checks tied to fund release | No outputs yet; publication unspecified | Designed to | Partly |
| ๐ช๐ธ Spain | Action-plan status column; draft three-yearly report | Action plan yes; report not in force | Yes (done / in progress / not started) | No |
| ๐ธ๐ช Sweden | None specific | โ | โ | โ |
| ๐ซ๐ฎ Finland | EU Art. 8(3) action plan | Linked by ECDC | Unknown | No |
| ๐ณ๐ด Norway | Directorate annual reports; parliamentary questions | Yes | No milestones | No |
| ๐ฉ๐ฐ Denmark | National audit office follow-up notes | Yes | Yes, closes points | Yes |
| ๐ฆ๐น Austria | Court of Audit annual follow-up | Yes | Yes, but self-reported and counts promises | Partly |
| ๐จ๐ญ Switzerland | Platform update, change log, annual steering decision | Update yes; decision record not found | No | No |
| ๐น๐ญ Thailand | Quarterly KPIs to management; SPAR | KPIs no; SPAR yes | No | No |
| ๐ฎ๐ฉ Indonesia | Agency self-monitoring; SPAR | Self-monitoring no; SPAR yes | No | No |
| ๐ณ๐ฌ Nigeria | NCDC annual reports; joint annual review; JEE | Yes, but inconsistent on NAPHS 2.0 | Partly | JEE yes |
| ๐ฎ๐ณ India | Proposed working group and scorecard; One Health Mission press releases | Scorecard not evidenced | No | No |
| ๐ง๐ท Brazil | Diretrizes organised by deadline "to facilitate monitoring" | No monitoring report | No | No |
| ๐ฎ๐ฑ Israel | State Comptroller | Yes (2020, 2024) | Yes, episodically | Yes |
Key patterns
- One-off outputs land; machinery slips. Institutions launched on a statutory date, Cabinet-approved documents and responses to inquiries arrive. What slips needs other levels of government, a legislative majority or recurring effort: implementing acts, plans co-produced with regions, operational builds, evaluations and progress reports.
- External calendars make reporting happen. Recurring reporting is delivered when an outside body sets the format and the date (WHO SPAR, JEE, the EU Art. 7 round, the UK Biological Security Strategy report). It slips when the cadence is self-imposed or merely requested.
- Quiet re-dating replaces admitting delay. Missed deadlines reappear with a new date in a forward-looking document. No jurisdiction publishes a variance log of original date, new date and reason.
- COVID-benchmarked targets are easy to meet. Many targets that were met were set against COVID-era capacity or old stock norms. Where targets reach beyond COVID, delivery is unreported or behind, and the most demanding capability targets fall due in 2027โ2030.
- The EU and WHO supply the deadlines. For about a third of jurisdictions the only hard dates come from outside: EU Regulation 2022/2371 action plans for member states, and WHO SPAR and JEE for the emerging economies.
- Audit offices have barely looked. Independent audit of current arrangements was found in only about seven places. Where it exists it moves delivery: both of Korea's on-time 2026 items were audit follow-ups.
- Unknowns follow the absence of a duty to publish. Nearly a third of past-due commitments cannot be judged. The cause is structural: no publication duty, internal-only tracking, classified annexes, or targets that start counting only once a pandemic is declared.
Full report and ledgers
The report gives a source for every status, the patterns in full, and corrections to earlier reports. The regional ledgers hold the item-level research notes.
- Pandemic strategies deliver paperwork, defer capability: full report (opens on GitHub in a new tab)
- Anglosphere ledger (UK, US, Canada, Australia, New Zealand) (opens on GitHub in a new tab)
- EU and big four ledger (EU, Germany, France, Italy, Spain) (opens on GitHub in a new tab)
- Nordic and Alpine ledger (Sweden, Finland, Norway, Denmark, Austria, Switzerland) (opens on GitHub in a new tab)
- East Asia ledger (Japan, South Korea, Taiwan, Singapore) (opens on GitHub in a new tab)
- Emerging economies ledger (Thailand, Indonesia, Nigeria, India, Brazil, Israel) (opens on GitHub in a new tab)